ADAS and Bluesky survey 30,000 km of overhead power lines using LiDAR technology

Oct 20, 2014 -- A multi million pound contract to produce the largest ever LiDAR survey undertaken by an electricity distribution network operator in the UK has been awarded to ADAS and Bluesky International. The companies have been contracted to conduct an aerial 3D LiDAR survey of the whole of UK Power Networks’ High and Extra High Voltage (HV & EHV) overhead power lines, which extend to over 30,000 kms.

LiDAR is a remote sensing technology that measures distance by illuminating a target with a laser and analysing the reflected light to produce high-resolution maps. The technology is central to the UK Power Networks contract, a three year risk-based tree clearance programme for the electricity company. The survey assesses the current state of vegetation near the overhead lines via the use of fully up to date 3D LiDAR images rather than aerial photography.

Tree related electrical disruptions present the single greatest risk to electricity supplies. For this reason, electricity industry regulators in many countries require proof that vegetation management systems are in place to minimise the potential for this type of incident and the impact on customers.

A major challenge of the contract was the need to complete the survey before autumn leaf fall started in earnest.  Weather conditions and Air Traffic Control restrictions can sometimes be unpredictable and add to the challenge. However, three fixed wing aircraft, each fully equipped with the world’s most advanced LiDAR sensors, have been in the air every day since mid July and successfully completed the survey within the strict deadline.

ADAS and Bluesky have a strong track record of working together on similar projects. The UK Power Network project follows on from a highly successful contract that the companies delivered for SP Energy Networks in 2013. It involved the use of stereo aerial photography to assess the amount of vegetation near the overhead lines combined with an assessment of the number of customers affected which informed a prioritised programme for resilience clearance.

Project team manager Roy Dyer says, “ADAS provides high level policy and operational advice to a number of electricity distribution network operators but this exciting new contract win proves that the combination of Bluesky’s aerial photography and LiDAR capability and ADAS’ knowledge and experience of vegetation management near overhead electricity lines provides the most comprehensive strategic vegetation service available.”

Rachel Tidmarsh, managing director of Bluesky International, says, “By combining Bluesky and ADAS’ expertise we have been able to offer an innovative and cost effective solution that provides UK Power Networks with highly detailed LiDAR, aerial photography, mapping and analysis of their overhead line assets enabling them to make more informed decisions regarding vegetation management.”

Through this project, UK Power Networks will be able to demonstrate to both the industry regulators and their customers that they have invested in the best available vegetation management system that will enable them to minimise tree related electrical disruptions.

Contacts:
Bluesky 
Robert Peel
tel +44 (0)1666 823306
Email Contact
www.bluesky-world.com

ADAS -
Admiral PR
+44(0)191 222 0722
Email Contact 



Read the complete story ...
Featured Video
Editorial
Jobs
Mechanical Engineer 2 for Lam Research at Fremont, California
Equipment Engineer, Raxium for Google at Fremont, California
Mechanical Manufacturing Engineering Manager for Google at Sunnyvale, California
Mechanical Test Engineer, Platforms Infrastructure for Google at Mountain View, California
Mechanical Engineer 3 for Lam Research at Fremont, California
Senior Principal Mechanical Engineer for General Dynamics Mission Systems at Canonsburg, Pennsylvania
Upcoming Events
Celebrate Manufacturing Excellence at Anaheim Convention Center Anaheim CA - Feb 4 - 6, 2025
3DEXPERIENCE World 2025 at George R. Brown Convention Center Houston TX - Feb 23 - 26, 2025
TIMTOS 2025 at Nangang Exhibition Center Hall 1 & 2 (TaiNEX 1 & 2) TWTC Hall Taipei Taiwan - Mar 3 - 8, 2025
Automate 2025 at Detroit, Michigan, USA MI - May 12 - 15, 2025



© 2024 Internet Business Systems, Inc.
670 Aberdeen Way, Milpitas, CA 95035
+1 (408) 882-6554 — Contact Us, or visit our other sites:
AECCafe - Architectural Design and Engineering EDACafe - Electronic Design Automation GISCafe - Geographical Information Services TechJobsCafe - Technical Jobs and Resumes ShareCG - Share Computer Graphic (CG) Animation, 3D Art and 3D Models
  Privacy PolicyAdvertise