Buying Policy
Average commitment lead time for Capital Expenditures increased by three days in February to 143 days. Average lead time for Production Materials decreased by one day in February to 64 days. Average lead time for Maintenance, Repair and Operating (MRO) Supplies decreased by one day in February to 31 days.
Percent Reporting | |||||||
|
|
|
|
|
|
|
|
Capital Expenditures | Hand-to-Mouth | 30 Days | 60 Days | 90 Days | 6 Months | 1 Year+ | Average Days |
Feb 2020 | 22 | 5 | 7 | 19 | 28 | 19 | 143 |
Jan 2020 | 22 | 4 | 10 | 20 | 25 | 19 | 140 |
Dec 2019 | 20 | 5 | 9 | 19 | 26 | 21 | 147 |
Nov 2019 | 20 | 6 | 11 | 16 | 27 | 20 | 144 |
|
|
|
|
|
|
|
|
Production Materials | Hand-to-Mouth | 30 Days | 60 Days | 90 Days | 6 Months | 1 Year+ | Average Days |
Feb 2020 | 10 | 34 | 28 | 19 | 7 | 2 | 64 |
Jan 2020 | 11 | 34 | 27 | 18 | 8 | 2 | 65 |
Dec 2019 | 11 | 33 | 28 | 20 | 6 | 2 | 63 |
Nov 2019 | 12 | 36 | 28 | 16 | 6 | 2 | 61 |
|
|
|
|
|
|
|
|
MRO Supplies | Hand-to-Mouth | 30 Days | 60 Days | 90 Days | 6 Months | 1 Year+ | Average Days |
Feb 2020 | 40 | 38 | 14 | 6 | 2 | 0 | 31 |
Jan 2020 | 40 | 36 | 14 | 8 | 2 | 0 | 32 |
Dec 2019 | 40 | 35 | 15 | 5 | 4 | 1 | 37 |
Nov 2019 | 41 | 36 | 16 | 4 | 3 | 0 | 31 |